Product1 distinct publisher3 min readUpdated
The forecast sits in the Electricity Statement of Opportunities, the document utilities and governments plan against. It arrives with a third of last year's project list already cancelled.
The Product Desk · Product desk

Compiled by The Product DeskSomething wrong?How this is made
Thirty-four terawatt hours a year, spread evenly across 8,760 hours, works out at about 3.9 gigawatts of continuous draw [18]. The size is not really the complaint. AEMO's stated reason for singling out this load is its shape: data centres run at much the same rate through the day and across the seasons, the way a large industrial site does [5]. Households and factories hand a planner a trough to work in. A hall of accelerators does not.
The report flags one trap before anyone else can fall into it. Roughly 13 gigawatts of coal and almost 2 gigawatts of gas are due to leave the system within the decade [4], but energy measured over a year and capacity measured at an instant are different quantities and do not subtract [17]. Comparing them honestly would need the capacity factor of the 9 gigawatts of generation and storage that reached full output in 2025-26 [7], and that number is not in the reporting.
There is a second figure inside the 13% that nobody has printed. If 34 terawatt hours is 13% of the market in 2035-36, the market itself is about 262 terawatt hours [19]. Run the same arithmetic backwards through the almost sevenfold rise and today's 3% share, and you get roughly 4.9 terawatt hours of data centre load now against a market of about 163 terawatt hours, which means AEMO's share figure only holds if total demand grows on the order of 60% [20]. So the 13% is a statement about electrification as much as about racks. If the rest of that growth arrives late, the same 34 terawatt hours becomes a larger slice of a smaller market, and the reliability problem worsens without a single extra server being installed.
Then there is the quality of the input. Developers have cancelled more than a third of the data centre projects AEMO listed a year ago [9]. Wires and transformers have no setting for that: the planning cycle is longer than the interval in which a third of a pipeline can disappear, and the same interval could see it refill. Commonwealth Bank puts the national buildout at as much as A$150bn, about $108bn, by 2030 [10], and the Clean Energy Finance Corporation has already named the failure mode if connections lag the load: bottlenecks, higher prices for consumers, and more reliance on fossil generation than was planned for [11].
The rulebook that would arbitrate any of this is not settled. The federal government is pushing for new data centres to run on renewable energy, and some regional administrations object [12]. Anthony Albanese is expected to use Wednesday's national cabinet to tell premiers that federal approval rules will complement state ones rather than override them, according to the Guardian [13]. Queensland and the Northern Territory have been the loudest objectors, and a climate expert told that paper Australia has "one shot to get the rules right" [14]. Australia's world-first data centre rules required every state to agree, and two refused in July [15]. Some builders are not waiting for a connection at all [16]. AEMO's own chief executive, Daniel Westerman, has framed the timing plainly: plenty of capacity is coming before the early 2030s, and the wave after 2030 is the one that decides reliability [8].
Follow any of these and your For You feed starts watching them — no settings page required.
Ranked by verification strength, evidence, and original report placement.
AEMO forecasts data centres will take 13% of Australia's main electricity market by 2035-36, up from 3% today, almost a sevenfold rise in a decade. Keira Wright reported the forecast for Bloomberg.
The figure appears in AEMO's annual Electricity Statement of Opportunities, the operator's read on whether supply will meet demand across the National Electricity Market over the coming decade, and the document utilities and governments plan against.
On AEMO's projection, data centres will draw 34 terawatt hours a year from the National Electricity Market by 2035-36.
Roughly 13 gigawatts of coal-fired plant will retire within the decade, along with almost 2 gigawatts of gas generation.
AEMO said in its report: "Data centers are particularly influential because they operate relatively consistently throughout the day and across seasons, similar to large industrial loads."
Generation and storage connections more than doubled last year's record, and AEMO says that has improved the reliability picture.
Evidence-backed comparisons of source perspectives and observed adoption signals. Read the methodology
Which Builder, Operator, and Investor concerns the observed source mix emphasized—not a truth score.
Evidence, demonstrated adoption, hype gap, incentives, and confidence are assessed independently, each on its own current evidence. How these are measured.
Named institutional report, single-outlet relay
The core numbers come from a specific, identifiable primary document (AEMO's Electricity Statement of Opportunities) with direct quotations from the report and its chief executive, plus named third-party figures from CBA and the CEFC. Against that, the cluster contains one publisher relaying Bloomberg and Guardian reporting rather than the report itself, and several supporting claims (the $28bn off-grid project, United States Studies Centre numbers, the European 63% figure) arrive without attribution or dates.
Real supply-side build, forecast-only demand
Concrete adoption evidence exists on the generation side: about 9 GW of new generation and storage reached full output in 2025-26, double the prior year. The data centre load itself is still mostly prospective, at roughly 3% of the market today, and the announced pipeline that supports the 2035-36 number lost more than a third of its projects in a single year. Policy adoption is incomplete, with unanimous-consent rules rejected by two states.
Headline multiple runs ahead of a discounted pipeline
The 'seven times more power' framing in the headline compounds a growth multiple off a small base (roughly 4.9 TWh implied today) and treats a demand projection as a trajectory, while the body concedes more than a third of the underlying project list has already been cancelled and that AEMO published a demand projection rather than a build schedule. The overstatement is modest because the article itself supplies the corrections, separates energy from capacity units, and reports the offsetting record capacity additions.
Interested parties on every side of the number
Each cited actor has a stake in the figure: AEMO's mandate and case for further investment rest on demand growth, CBA is a lender sizing a A$150bn buildout, the Clean Energy Finance Corporation is a green investor warning about fossil reliance and consumer prices, and federal and state governments are actively contesting who approves data centres and on what energy terms. Developers cancelling a third of their announced projects also had incentives to announce them in the first place. The publisher's own incentives are not disclosed in the source.
Solid primary document, thin cluster
Confidence is supported by the specificity and provenance of the central figures and by the article's transparency about what the forecast does not settle. It is capped by the cluster containing a single publisher with no independent verification, by second-hand relay of Bloomberg and Guardian reporting, by unattributed supporting claims, and by the absence of any scenario range around the 13% central case.
product
Meta owns the models and the data centres, and still pays Microsoft to rent someone else's1 distinct publisher
leadership
Your Face Is Now Inventory: ASIC Logged 19,400 Scam Reports and $7.4m Lost to Ten Deepfaked Figures1 distinct publisher
product
Nebius funds $4.5bn of AI capacity on terms that pay lenders mostly in stock2 distinct publishers
product
Lammermuir arithmetic: £2bn of data centre against 10,000 signatures, before an application exists1 distinct publisher
Distinct publishers with included, body-backed reporting in this cluster.
1 article · August 24, 2026