Two of Taiwan's 66 F-16V jets reach Taitung after delay at Hawaii base

Taiwan has received the first two of 66 F-16 Block 70 jets it ordered from the US in 2019 for $7.76 billion, after a six-week stop in Hawaii. The other 64 are due by the end of 2026, on a schedule that has already slipped.

The Product Desk · Product desk

Photograph accompanying Two of Taiwan's 66 F-16V jets reach Taitung after delay at Hawaii base
Photo: focustaiwan.tw

What happened

  • The jets left the US mainland on August 17 and reached Joint Base Pearl Harbor-Hickam in Hawaii four days later, on August 21.
  • They were meant to fly on within days, and no official reason has been given for the hold; the report lists technical problems, weather and tanker availability as plausible causes.
  • Interesting Engineering attributes the wider program delay to a production-line relocation combined with supply-chain disruptions.
  • Taiwan's ruling DPP welcomed the arrival, while opposition Kuomintang legislators questioned why the order is running so late.
  • A separate $14 billion US arms package for Taiwan is also still waiting for Washington's approval.

Compiled by The Product DeskSomething wrong?How this is made

Why it matters

  • constraint Taiwan's air force cannot treat end-2026 as a firm date for squadron planning while 64 of the 66 jets are still to come and the latest hold has no stated cause.
  • exposure Each further slip gives the opposition a new count of jets ordered and not delivered, and the ruling DPP is the party that has to answer for that count.
  • precedent If the Hawaii hold was timed around Xi's visit, a suggestion the report calls speculation, delivery dates for the remaining jets would depend on the diplomatic calendar as well as the factory.

Two fighters at Chihhang Air Base in Taitung are, for now, all Taiwan has to show for an order it signed in August 2019 under the first Trump administration [1][3]. Ma Wen-chun, an opposition Kuomintang legislator, summed up the buyer's position in one line. "Two have arrived; the remaining 64 must arrive on time," Ma said [10].

On paper, the contract is 66 airframes for $7.76 billion, with every jet delivered by the end of 2026 [2][8]. So far two have arrived. That is about 3 percent of the order, with 64 still to come [1][2]. The window from signature to scheduled completion is roughly seven years and four months [3]. According to Interesting Engineering, delays meant only this first batch has arrived this year [4].

The jets were originally due in late August, ahead of a planned state visit to the US by Xi Jinping [5]. One explanation offered for the stop in Hawaii is that Washington wanted to avoid a "politically sensitive" delivery just before that visit. The report calls this speculation [14].

The report's own timeline does not add up. It dates the arrival to Friday, September 2, only 12 days after the jets landed at Hickam. Six weeks from August 21 is about October 2 [16][4].

Who the two jets are for affects what the wait costs. Taiwan already flies 1990s-era F-16A/B Block 20s. Most have been upgraded over time, and some are on par with the F-16V [7]. The new aircraft have the APG-83 AESA radar, modern avionics and longer-life airframes [6]. Some of the older fleet already has the upgraded standard. For that reason I'd expect each new delivery to count mainly as one more airframe with more years of service left. Taiwan's F-16 fleet only passes 200 once all 66 are in [8].

The evidence covers this one fighter contract and one other package, worth $14 billion, that is still awaiting approval [15]. It does not measure delivery performance across US arms programs.

Anyone holding a supplier to a delivery date can sort each order with two questions. The first is what share of the units ordered has physically reached the customer. The second is whether each delay has a stated cause. A late order with a named cause and a rising share can be replanned with a new date. A delay with no stated cause cannot be replanned, and any completion date that depends on one should be treated as unconfirmed. On this order, 3 percent of the jets have arrived [2]. The program delay has a stated cause, but the six weeks at Hickam still have none [11][13].

What to watch

  • An official US or Taiwanese explanation for the six-week hold at Joint Base Pearl Harbor-Hickam.
  • The date and size of the next F-16 Block 70 batch, measured against the end-2026 completion date for all 66 jets.
  • Whether the separate $14 billion US arms package for Taiwan moves to approval.