Treetop's 1,000MW grid filing set off East Fishkill's three-year data-centre ban

East Fishkill, New York, unanimously barred data centres over 20MW until July 2029, though no developer had applied to build one. The plan surfaced in a filing with New York's grid operator, so opposition reached the town board before any application did.

The Board Room · Leadership desk

How we use AISend a correction

Photograph accompanying Treetop's 1,000MW grid filing set off East Fishkill's three-year data-centre ban
Photo: wamc.org

What happened

  • The requested load would exceed the electricity use of Buffalo, a city of about 275,000, in a town of 30,000 people.
  • Supervisor Nick D'Alessandro said standalone data centres were not a permissible use under the town's zoning even before the ban.
  • Organiser Melissa Hoffmann said months of public pressure turned a seven-month pause under discussion into a three-year moratorium.

Compiled by The Board RoomSomething wrong?How this is made

Why it matters

  • constraint Until July 2029 the town cannot consider any data centre above 20MW, one-fiftieth of Treetop's request, so mid-sized projects are shut out along with the giant campus.
  • exposure A developer that files with the grid operator before making a local case can meet organised opposition first, as Treetop's queue request drew residents to the board before any application existed.
  • precedent Town boards now have a model for imposing a moratorium even where zoning already forbids the use, justified as certainty and time for study.

In East Fishkill the grid operator heard about the project before the town did. Residents discovered that Treetop, through a local property owner called Donovan Drive Holdings, had asked for roughly 1,000 megawatts of electrical service on land it had bought while seeking approval for a warehouse [11]. The request went to the New York Independent System Operator, which manages the state's high-voltage grid and must give permission for any massive new connection [12]. It did not go to the town [12]. For residents, the filing quickly raised concerns [16].

A skeptic would say the moratorium was redundant, and the town supervisor came close to saying so. "There is no application before the Town. There has never been an application for a datacenter," Nick D'Alessandro wrote on Facebook in June [2]. He later took the post down, and his office did not respond to the Guardian [2]. Zoning already barred large data centres [1]. The board banned them for three years anyway, "to give our community certainty and allow time for further study and discussion" [3].

The text of the ban answers the skeptic. The zoning code limited what could be built. The moratorium, adopted unanimously in late June, forbids the town from even considering any new data centre above 20 megawatts until July 2029 while officials study effects on water and local ecosystems [7]. That threshold is one-fiftieth of the roughly 1-gigawatt campus Treetop was exploring [5][17], so it reaches projects far smaller than this one. The developer has appealed [8]; the Guardian's account does not say where or on what grounds.

East Fishkill shows that local opposition can arrive before the town's zoning or the grid request is ever tested. Whether it ends the project is still open. The backlash began before a single permit application was filed [6]. "Residents have been speaking out against it to stop any application from coming into the town for the datacenter," said Melissa Hoffmann, an organiser with a local chapter of Food & Water Watch [14]. By her account, that pressure made the pause about five times longer than first discussed [18]. Against that, zoning already excluded the use [1], and the developer is still contesting the ban [8].

The opposition came from a town that built chips. IBM researched and made semiconductors on a 460-acre campus there for nearly fifty years [4]. "This is not an anti-tech town," said Tanya Radford, a resident and professor. "I'm an educator. I use technology." [10] Her concern was speed. "I just think that we're at this moment where things are happening very quickly, we need to get our ducks in a row," she said [9]. The Guardian places the fight within a wider split, in which rural towns and former tech hubs alike question whether AI infrastructure brings enough local benefit for the electricity, water and land it uses [19].

For a developer choosing sites this quarter, the decision this case forces is the order of filings. The trade-off in East Fishkill was an early start on the grid connection against months in which the town board heard objections before it saw any proposal [6][12]. Next quarter's consequence for Treetop is a 1,000MW grid request in a town barred from considering it until July 2029, unless the appeal succeeds [7][8][11].

What to watch

  • The ruling on Treetop's appeal of the moratorium, and the forum and grounds on which it was filed.
  • Whether Treetop keeps its roughly 1,000MW request in NYISO's interconnection queue while the town is barred from considering a data centre.
  • What the town's study of water and ecosystem effects concludes before July 2029, and whether the 20MW threshold survives it.

Clarity's read

What the record supports and how the coverage leans. The claims behind it follow.

Reality

Evidence55
Adoption
Insufficient
Hype gap+10
Incentives45
Confidence55
Why these scores

Claim ledger

Ranked by verification strength, evidence, and original report placement.

  1. [1]

    Even before any plans for the facility were drawn up, East Fishkill's existing zoning laws did not allow for the construction of large data centers.

  2. [2]

    "There is no application before the Town. There has never been an application for a datacenter," East Fishkill supervisor Nick D'Alessandro wrote on Facebook in June; he later took down the post, and his office did not respond to the Guardian's request for comment.

    ReportedSupportedSource: Nick D'Alessandro, via the Guardian2 sources— create a free account to open themView cited source
  3. [3]

    D'Alessandro stressed that standalone datacenters were "not even listed as a permissible use" under the town's zoning laws; in June the board banned their construction for three years "to give our community certainty and allow time for further study and discussion".

    ReportedSupportedSource: Nick D'Alessandro and the town board, via the Guardian2 sources— create a free account to open themView cited source

Sources

1 independent publisher whose own reporting we read for this story.

  1. theguardian.com

    1 article · October 9, 2026

    ‘This is not an anti-tech town’: backlash to datacenter in city once home to IBM

Share your take

Let Clarity write the post for you.

Signed-in readers get a short post drafted on this story in the register they choose — narrative, analytical, or a direct position — editable to the last word before it goes anywhere. The share buttons at the top of this story work without an account.

Topics and entities

Follow any of these and your For You feed starts watching them — no settings page required.

Entities

Loading related stories