ProductNot yet confirmed elsewhere1 publisher3 min readPublished
Ofgem wants a deposit developers cannot claw back, and the queue's 84GW says why
The UK grid connection queue went from 41GW to 125GW while land and planning gates were already in force. Ofgem's answer is a nonrefundable fee, at a price not yet set.
The Product Desk

What happened
- Ofgem published a proposal in July aimed at clearing phantom data centre projects out of the grid connection queue, with industry feedback closing in September.
- The central instrument is a nonrefundable connection deposit that could reach hundreds of millions of dollars for the largest sites.
- Applicants would also have to line up customers in advance and prove they can fund the build.
- Ofgem says queued demand rose from 41GW in November 2024 to 125GW in June 2025.
Why it matters
- exposure The flip-the-slot trade Darmouni describes depends on cheap entry; a fee that cannot be recovered strands its inventory rather than reselling it at a premium.
- decision Anyone holding UK land without a signed tenant now chooses between finding one first and taking the project to a market where a queue place still costs little.
- constraint Until Ofgem names the fee, no UK site can be priced properly, because the cost of holding a connection is an open variable in every model.
- contradiction The state designated data centres critical national infrastructure just before the queue swelled, and now says much of the demand behind that swelling is imaginary.
Joining the queue cost a few thousand dollars, the wait was years long, and holding the slot cost nothing more, so developers held it whether or not they had a plan [4]. The word doing the work in Ofgem's proposal is nonrefundable [2]. A large refundable deposit is a treasury problem, solvable by anyone with a credit line. A nonrefundable one is an expense booked against a named site, and coupled with the demand for customers and funding up front [3], it requires the commercial case to exist before the connection does.
The size of the repricing is roughly five orders of magnitude at the top end, from a few thousand dollars to potentially hundreds of millions [20]. Nothing about a developer's queue behaviour survives that unchanged.
There is already evidence about which gates work. Since 2024, applicants have had to show secured land rights, a submitted planning application, and other milestones [8]. Those tests were in force while the queue's total demand climbed from 41GW to 125GW, an increase of 84GW in about seven months [5][17]. Paperwork you can buy from a planning consultant does not deter a free hedge.
The bill for the phantom entries lands on other people's schedules. Because operators must study the combined effect of large proposals on network stability before granting any single connection, each junk application makes the studies for viable projects longer, costlier and more complex, according to Olivier Darmouni of HEC Paris [9]. He also describes the secondary market the wait created: middlemen apply for power in order to flip land at a premium with a connection attached, which he likens to ticket scalping [10]. Neara's Taco Engelaar says nobody really understands what the real grid demand is because of the phantom projects [15]. WIRED reports the jam is both stretching wait times for viable schemes and fouling demand forecasting and expansion planning [16].
The arithmetic shows what forecasters are working with. New data centres account for 73GW of the 125GW queue, about 58 percent [5][6][18]. Ofgem's own comparison, that 73GW is one and a half times last year's UK peak, implies a national peak of roughly 49GW [6][19], which makes the queue about 2.6 times everything the country actually drew at its highest [21].
What is unresolved is the price. Ofgem's Nathan Macwhinnie says connecting viable data centres more quickly is an enabler of the UK's AI ambitions [13], and the regulator says it will weigh industry concerns before settling on a fee, while noting that energy markets do not compare like for like across borders [14]. Industry's read, per WIRED, is that the reforms risk making a country already hampered by expensive power and scarce land one of the world's costliest places to build [22]; Knight Frank's Alex Burgoyne warns against shooting the golden goose [12]. One rule, two outcomes, separated by a number nobody has written down yet. And the proof-of-customer test cuts wider than the scalpers it is aimed at: a developer building capacity ahead of a signed tenant fails it on the same terms [3].
What to watch
- The fee Ofgem lands on once feedback closes in September, and whether it scales with requested capacity or sits flat.
- The next Ofgem queue figure: whether the 125GW total falls after deposits apply, and by how much.
- Whether the 2024 milestone tests survive alongside the deposit or are folded into it.
Clarity's read
What the record supports and how the coverage leans. The claims behind it follow.
Reality
- Evidence62
- Adoption28
- Hype gap+12
- Incentives72
- Confidence55
Claim ledger
Ranked by verification strength, evidence, and original report placement.
- [1]
In July, Ofgem laid out a proposal meant to force phantom data centres out of the UK grid connection queue, set to be finalised after an industry feedback process that ends in September.
- [2]
Under Ofgem's plans, developers would be required to put down a steep, nonrefundable deposit that could balloon to hundreds of millions of dollars for the very largest data centres.
- [3]
Developers would also be required to line up customers in advance and prove they have the funding to complete their builds.
- [4]
Because developers face a years-long wait for grid access and it has previously cost only a few thousand dollars to join the queue, applying for power without a watertight development plan was a no-downside bet.
- [5]
Between November 2024 and June 2025 the total energy demand of projects in the UK connection queue increased from 41 gigawatts to 125 gigawatts, according to Ofgem.
- [6]
New data centres make up 73 gigawatts of the queued demand, equivalent to one and a half times the peak demand for the entire UK last year.
- [7]
The queue to join the UK grid began to balloon toward the end of 2024, around the time the government designated data centres critical national infrastructure.
- [8]
Since 2024 the UK has required all developers to demonstrate they have at least secured land rights, submitted a planning application, and met other milestones.
- [9]
Grid operators must account for the combined effect of large infrastructure proposals on network stability before granting individual connections; Olivier Darmouni of HEC Paris Business School says speculative projects are especially damaging because they make these studies more complex, more expensive and longer.
- [10]
Darmouni says a lengthy queue attracts middleman developers who apply for power aiming to flip land at a premium packaged with grid access, calling it like scalping for concert tickets.
- [11]
The UK government has said it believes much of the queued demand is a mirage.
- [12]
Alex Burgoyne, head of data centres at Knight Frank, says the buildout is bringing a huge amount of capital investment into the UK and that "we don't want to shoot the golden goose".
- [13]
Nathan Macwhinnie, Ofgem's deputy director of strategic planning and connections, said data centres are a key part of the UK's AI ambitions and future economic growth, and that enabling viable data centres to connect more quickly is an enabler of this.
- [14]
Ofgem says it will take industry concerns into account before settling on a fee, but that differences between international energy markets make like-for-like comparison difficult.
- [15]
Taco Engelaar, managing director at grid optimisation company Neara, says no one really understands what the real grid demand will be because of the phantom projects.
- [16]
The queue jam is exacerbating already years-long wait times for viable projects and is interfering with attempts to forecast energy demand and plan grid expansions.
- [17]
The queued demand grew by 84 gigawatts between November 2024 and June 2025, a span of about seven months.
- [18]
New data centres account for about 58 percent of the 125 gigawatt queue.
- [19]
If 73 gigawatts equals one and a half times last year's UK peak demand, that peak was about 49 gigawatts.
- [20]
Moving the cost of a queue place from a few thousand dollars to potentially hundreds of millions is a change of roughly five orders of magnitude at the top end.
- [21]
The 125 gigawatt queue is about 2.6 times the implied 49 gigawatt UK peak demand.
- [22]
Industry experts believe Ofgem's reforms risk making the UK, already unattractive for the high cost of energy and dearth of land, one of the world's most expensive places to build a data centre.
- [23]
Data centre developers face delays almost everywhere, with similar grid congestion in the US and across Europe, but the US is a highly desirable market.
Sources
1 independent publisher whose own reporting we read for this story.
- wired.comThe UK Power Grid Has a Phantom Data Center Problem
1 article · August 26, 2026
Topics and entities
Follow any of these and your For You feed starts watching them — no settings page required.