Product1 distinct publisher3 min readPublished
US data centres drew about 25GW in 2024, and BloombergNEF has them at 106GW by 2035. On that arithmetic, the question for anyone planning a cluster is when the megawatts arrive, not when the GPUs ship.
The Product Desk · Product desk

Compiled by The Product DeskSomething wrong?How this is made
Run the units and the projections stop being abstract. A 100MW IT campus running flat out consumes on the order of 876GWh a year [6]. McKinsey's 606TWh figure for US data centres in 2030 [2] divides into roughly 690 of those campuses [1]. That is what a terawatt-hour looks like on the ground: several hundred fully loaded halls, each needing its own connection and its own energisation date.
Capacity plans tend to be written in hardware. GPUs land in Q3, cluster in production by Q4. What the schedule actually waits on is the interconnection agreement, and the Data Center Dynamics column that gathers these forecasts describes queues stretching for years and new high-voltage transmission taking most of a decade to permit and build [7]. The Department of Energy and Lawrence Berkeley National Laboratory put data centres at roughly 50GW of the new peak capacity the grid has to add by 2030 [3], about twice what the sector drew in total in 2024 [6]. Everyone in that queue holds a purchase order for the same thing.
Then there is firmness, which is where the cheap answers fail. Wind runs at a 30-40 percent capacity factor and solar at 20-30 percent [10]. Covering 100MW of continuous load from solar alone means sizing 333MW to 500MW of nameplate [3], plus storage for the hours after sunset. Nuclear runs above 90 percent of the time, but a new plant takes five to ten years or more [11], which outlasts the roadmap it would serve. Gas is dispatchable and quick to build, which is why new plants are being announced specifically to serve data centres behind the meter [14], and turbine order books are already backlogged into the late 2020s [13]. The economics run one way only: an idle GPU is a depreciating asset, so curtailment lands on the compute P&L rather than the energy line [15].
Two axes decide the source, per the column: whether it delivers around the clock, and what it costs the climate [17]. A third belongs on the grid for anyone planning capacity, which is time to first electron. Cross firm-versus-intermittent with on-grid-versus-behind-the-meter and the four boxes fail differently. Firm and on-grid means waiting in the queue; firm and behind the meter means gas today, and a carbon number the same team answers for later. Intermittent and on-grid puts curtailment against depreciating hardware; intermittent and behind the meter is a storage bill.
What the column does not supply is the operator's half of the evidence: no queue durations in months, no prices, no named contract with a megawatt figure and a date. Its own 130 percent US demand growth projection is credited only to unnamed "other analysts" [5]. Treat the aggregate as direction rather than schedule, and put three fields beside each compute increment in your own plan: firm megawatts, source and capacity factor, energised-by date. A blank in any of the three makes the GPU date a guess.
Ranked by verification strength, evidence, and original report placement.
US data centers drew roughly 25GW in 2024, and BloombergNEF projects that figure could reach 106GW by 2035, more than quadrupling the sector's appetite in a decade.
McKinsey pegs US data-center consumption at 606TWh by 2030, up from about 147TWh in 2023, or close to 12 percent of the nation's electricity.
The Department of Energy and Lawrence Berkeley National Laboratory estimate data centers account for roughly 50GW of the new peak capacity the grid must add by 2030, and could consume up to 12 percent of US electricity by 2028.
The International Energy Agency expects global data-center electricity use to more than double to roughly 945TWh by 2030, with the United States driving the single largest increase.
A single 100MW IT campus running flat out consumes on the order of 876GWh a year, and can produce tens to hundreds of millions of AI tokens per second.
Interconnection queues stretch for years, transmission is congested, and new high-voltage lines take most of a decade to permit and build.
Distinct publishers with included, body-backed reporting in this cluster.
1 article · September 6, 2026
Follow any of these and your For You feed starts watching them — no settings page required.
invest
Behind-the-meter gas is the data center buildout's real cost: 318 Mt a year1 distinct publisher
product
HTS feeders trade parallel MV runs for a cryogenic plant that never gets to stop1 distinct publisher
science
Oak Ridge hands its nickel-hungry pennycress screen to an agentic co-scientist1 distinct publisher
product
PJM can now reach inside the fence, and your grid signal is a production change1 distinct publisher
Evidence-backed comparisons of source perspectives and observed adoption signals. Read the methodology
Which Builder, Operator, and Investor concerns the observed source mix emphasized—not a truth score.
Evidence, demonstrated adoption, hype gap, incentives, and confidence are assessed independently, each on its own current evidence. How these are measured.
Named institutions, single relay
BloombergNEF, McKinsey, the Department of Energy with Lawrence Berkeley, and the IEA all carry weight here, and their numbers agree on direction from different starting points, which is the best thing this reporting has going for it. Every one of them reaches the reader second-hand through a single opinion column, with no study title, date, or link, and the steepest figure in the piece belongs to unnamed analysts.
Trend asserted, nothing countable
The procurement section describes behaviour only in the aggregate: order books backlogged, idled reactors eyed for restart, small modular reactors attracting real capital, gas plants announced for data centres behind the meter. No operator, developer, site, contract, or megawatt total appears, and nothing is dated, so there is no way to tell a handful of pilots from a build-out.
Sober arithmetic, headline reach
The demand numbers are conservative and hold together; the step from them to a power problem that will decide the AI race is the author's own, and the column concedes as much by phrasing it as an argument. Geothermal gets promoted to the sleeper of the mix on capacity factor and footprint alone, with no drilling time, cost, or count of viable sites to weigh against nuclear or gas.
Trade outlet, industry readership
DataCenterDynamics serves the industry whose expansion this column says is power-limited, and the piece is filed as opinion, so its framing is closer to advocacy than to reporting. Against that, no vendor, developer, or sponsor appears in the text, and no forecast is sourced to a party selling equipment. The geothermal case is where a reader would most want an author affiliation, and none comes with the piece.
Consistent inside, unverified outside
A single publisher, a single opinion column, and no independent restatement of any figure keeps this on the low side. The internal corroboration is real: four forecasters with different methods land on the same order of magnitude. The specifics are what stay open, including which year data centres actually reach 12 percent of US electricity and how much of the projected 106GW is meant to sit behind the meter.