Texas's data center permit freeze could delay Chevron's 3-gigawatt Kilby decision to 2027
Chevron says Gov. Greg Abbott's moratorium on new data center permits could delay the investment decision on its nearly 3-gigawatt Kilby project until 2027. For one of the largest new US data center projects, the date now depends mainly on a state permit.
The Investor · Invest desk

What happened
- Preliminary earthmoving is already underway at the West Texas site while Chevron and Joulent finalize construction contracts and wait for final state permits.
- Chevron's Daniel Droog said Kilby remains on track to produce its first electrons by 2028 despite the possible delay to the investment decision.
- Joulent was formed from Engine No. 1, which bought gas turbines years ago before the supply crunch, so the project already has its most essential hardware.
- Joulent has hired two former executives from LNG exporter Cheniere into C-level leadership roles, Semafor reported.
Compiled by The InvestorSomething wrong?How this is made
Why it matters
- cost Chevron wants Kilby as an anchor customer for Permian gas that is practically treated as waste. That customer arrives with first power, so a later investment decision costs the gas business little unless 2028 slips.
- decision Texas developers without Kilby's own power supply or pre-bought turbines face the same freeze with less to offer against Abbott's prerequisites, and Semafor's analysis says they should temper their pacing expectations.
- constraint With Senate Democrats blocking the federal bill on data center power costs, states such as Texas keep setting the terms for these projects through their own permits.
Two executives on the same project gave Semafor two different timetables. Michael Wortley, Joulent's new CFO, said the construction contracts are "a couple weeks, if not days, away" [9]. Daniel Droog, Chevron's vice president for power solutions, said the final investment decision, originally expected by the end of this year, could move to 2027 after the moratorium Abbott imposed last month [4][2]. The contracts are nearly signed and the turbines are owned [11]. What separates those two timetables is the final state permit [3].
Droog kept 2028 as the date for first electrons [6]. Suppose the decision moves into 2027 and that date holds. The time between committing to the build and producing power then gets shorter by however long the delay lasts, unless the earthmoving already underway absorbs some of it [1]. Semafor did not report the project's cost, the value of the construction contracts, or the price Microsoft pays under its offtake [12]. On the record so far, the money spent has gone to preliminary earthwork and to turbines Engine No. 1 bought years ago [3][11].
Droog described the slowdown as industry-wide. Across AI infrastructure in Texas, he said, "the permitting and regulatory side has caused some slowdown or potential delay in the system" [5]. Semafor's analysis went further, arguing that "politics remain a bigger roadblock than capital, hardware, or workforce" [13]. Kilby is a fair test of that sentence. On Semafor's own account, two of the three are covered there: the 20-year Microsoft offtake on the money side [12] and the owned turbines on the equipment side [11]. One project and one company's account support the claim for Kilby. They say much less about Texas data centers in general.
Texas could grant the permits soon, as Wortley expects. "If you're part of the solution rather than the problem, ultimately you'll get your permits," he said [10]. Or the moratorium eases after the November elections, as Semafor's analysis expects for both the Texas and New York moratoria [14], and the delay lasts a few months. Or the freeze holds through 2027 and the 2028 date moves with it. I'd put Kilby in one of the first two. It generates all its own power and does not raise electricity costs for other customers on the local grid [7], and Wortley says that is what Abbott's prerequisites reward [10]. The counter-case comes from Chevron itself: with all of those advantages, its own executive still raised the possibility of 2027 [4].
The permitting thesis fails for Kilby if the investment decision lands before the end of this year. If the 2028 first-power date moves as well, the freeze will have cost the project more than a rescheduled board vote [4][6].
What to watch
- Whether Joulent announces signed construction contracts on the "a couple weeks, if not days" timeline its CFO gave.
- Whether Texas issues Kilby's final permits while the moratorium on other new data center permits remains in place.