NTT Data nears a deal to build Anthropic's Osaka data center for up to 1 trillion yen
NTT Data is in advanced talks to build Anthropic's first dedicated Japan data center in Osaka for up to $6.3 billion. The Nikkei's 500 MW power intake figure would equal half the 1 GW NTT targets for fiscal 2033, if the two measures are counted alike.
The Investor · Invest desk
Three figures, each a different measure: the Osaka data centre's power intake of up to 500 MW, per the Nikkei; NTT's domestic data center IT power capacity goal of around 1 GW by fiscal 2033, per cryptobriefing; and NTT's capacity expansion investment of over $9 billion, per cryptobriefing.
| Figure | Value | Note | Claim |
|---|---|---|---|
| Osaka data centre power intake, up to (Nikkei) | 500 MW | 3 | |
| NTT IT power goal, FY2033 | 1 GW, around | 12 | |
| NTT expansion investment | $9 billion over | 13 |
What happened
- The Nikkei reported that NTT Data and Anthropic aim to sign an agreement by the end of fiscal 2026, which ends March 31.
- Partial operations at the Osaka site are set to start as early as 2028, according to the same report.
- NTT's capacity plan is backed by investment of more than $9 billion, according to cryptobriefing.
- NTT declined to comment on the report, and NTT Group was not immediately available.
Why it matters
- exposure NTT's Osaka build would depend on one AI developer's demand, since Anthropic is the anchor customer of a facility built for a single tenant.
- cost If the build falls inside NTT's $9 billion-plus investment, the Osaka ceiling would take up to 70% of it and leave the remainder for everything else in the plan.
- contradiction The Nikkei words 2028 as the earliest start and cryptobriefing words it as the target, so the two outlets differ on how firm the date is.
- precedent One negotiation does not show AI labs moving to single-tenant regional capacity; a second lab-specific build elsewhere would.
Start with the units, because the two sources use different ones. The Nikkei's 500 MW is power intake [3]; NTT's own target is IT power capacity, about 300 MW today and about 1 GW by fiscal 2033 [12]. Set one against the other anyway (the measures differ, so treat the ratios as rough) and the Osaka site comes to 50% of the 1 GW end point and 71% of the 700 MW NTT has to add [16][17]. Against OSK11, the 30 MW Kansai facility NTT opened in April 2026, it is 16.7 times the size [7][15].
We think the reading that matters is concentration. If the site counts toward the plan, one tenant would take most of the capacity NTT intends to add, and NTT would have less to offer the many colocation customers behind its position as Japan's leading provider [14]. That view fails in two ways: if the signed capacity comes in well under 500 MW, or if the site sits outside the 1 GW plan altogether.
The counter-thesis starts from the fact that both headline numbers are ceilings. Cryptobriefing calls the $6.3 billion a ceiling estimate and says the deal is not finalized [5]; the Nikkei says costs could reach 1 trillion yen [2]. Divide $6.3 billion by 500 MW and the ceilings imply $12.6 million per MW [11], a figure that moves if cost and capacity do not land at their limits together.
Neither source says whether the site counts toward NTT's 1 GW plan, who funds the construction, or on what lease terms. The answer decides whether the money is NTT's to spend or is recovered from Anthropic.
Timing is the other place this can go differently. Cryptobriefing lists the inputs that move a data center date: power availability, equipment supply and permitting [8]. A signature at the fiscal year-end [6] would leave all three less time to settle before any 2028 start [10].
What to watch
- A signed agreement by March 31, and whether the contracted capacity matches the 500 MW the Nikkei reported.
- Disclosure of who funds the construction and on what lease terms, which would show whether the 1 trillion yen sits with NTT or Anthropic.
- Whether NTT counts the Osaka site toward its 1 GW fiscal 2033 target when it next reports capacity.
Clarity's read
What the record supports and how the coverage leans. The claims behind it follow.
Reality
- Evidence45
- Adoption15
- Hype gap+15
- Incentives
- Insufficient
- Confidence60
Perspective Coverage
8 publishers- Builder
- Builder 29%
- Operator
- Operator 28%
- Investor
- Investor 43%
Claim ledger
Ranked by verification strength, evidence, and original report placement.
- [1]
The Nikkei reported on Tuesday, Oct 13, citing multiple sources, that NTT Data Group, a unit of NTT, is in the final stages of talks to build a data centre in Osaka for Anthropic; cryptobriefing separately describes the talks as advanced negotiations.
- [2]
Construction costs could reach up to 1 trillion yen ($6.3 billion), the Nikkei report says.
- [3]
The Osaka data centre would have power intake capacity of up to 500 megawatts.
- [4]
NTT declined to comment, and NTT Group was not immediately available for comment.
- [5]
The deal is not finalized, and the $6.3 billion figure is a ceiling estimate.
- [6]
NTT Data and Anthropic aim to sign an agreement by the end of fiscal 2026, which ends on March 31.
- [7]
In April 2026 NTT opened the Kyohanna OSK11 data center in the Kansai area, with a capacity of 30 MW.
- [8]
Data center timelines depend on power availability, equipment supply and permitting, any of which can slip; cryptobriefing describes partial operations as targeted for 2028.
- [9]
Anthropic would be the anchor customer for the Osaka site, which would be its first dedicated data center in Japan and be built for a single AI developer.
- [10]
Partial operations at the Osaka data centre are set to start as early as 2028.
- [11]
The two ceilings imply about $12.6 million of construction cost per MW of power intake.
- [12]
NTT wants to grow its domestic data center IT power capacity from approximately 300 MW to around 1 GW by fiscal year 2033.
- [13]
NTT's capacity expansion is backed by an investment exceeding $9 billion.
- [14]
NTT already holds the position of Japan's leading colocation provider.
- [15]
The Osaka site's 500 MW power intake is about 16.7 times the 30 MW capacity of OSK11.
- [16]
500 MW is 50% of NTT's 1 GW fiscal 2033 target, if intake and IT capacity are counted alike.
- [17]
500 MW is about 71% of the 700 MW NTT plans to add to reach 1 GW from about 300 MW, if intake and IT capacity are counted alike.
- [18]
The $6.3 billion ceiling is at most about 70% of an investment exceeding $9 billion, if the Osaka build falls inside it.
Get this ledger inside ChatGPT. Ask about any of our stories and the answer brings its figure, each claim’s verdict and the sources. Free, no account.
Sources
5 independent publishers whose own reporting we read for this story.
- asia.nikkei.comSources: NTT Data is in advanced talks to build a data center for Anthropic in Osaka of up to 500 MW, among Japan's largest, potentially costing $6.3B
1 article · October 12, 2026
- channelnewsasia.comNTT Data in final talks to build Anthropic's first data centre in Japan, Nikkei reports
1 article · October 12, 2026
- cryptobriefing.comNTT in talks to build Anthropic’s first Japan data center at up to $6.3 billion
1 article · October 12, 2026
- datacenterdynamics.comNTT to build $6.3bn data center for Anthropic in Japan - report
1 article · October 13, 2026
- dealstreetasia.comNTT Data finalising talks to build Anthropic's first Japan data centre
1 article
- economictimes.indiatimes.comNTT Data: NTT Data in final talks to build Anthropic's first data centre in Japan, Nikkei reports - The Economic Times
1 article · October 12, 2026
- en.sedaily.comNTT in Talks With Anthropic on ¥1 Trillion Osaka Data Center
1 article · October 13, 2026
- thenextweb.comNTT Data reportedly nears deal to build Anthropic’s first Japan data centre
1 article · October 13, 2026
Topics and entities
Follow any of these and your For You feed starts watching them — no settings page required.
Topics
- Japan digital infrastructureFollow
- AI Data CentersFollow
- AI Compute Capacity and CostFollow