Anthropic's 20-year lease prices TeraWulf's Kentucky capacity at $2.4m per megawatt a year
Rothschild Redburn began coverage of TeraWulf at Neutral with a $15 target in August 2026. The company has 102 megawatts operating against 839 contracted, and its lease revenue runs at about 13% of what the Anthropic contract will eventually pay.
The Investor · Invest desk

What happened
- Rothschild Redburn initiated coverage of TeraWulf at Neutral with a $15 price target in August 2026, with most of the company's revenue now coming from leasing computing capacity rather than mining Bitcoin.
- HPC lease revenue hit $31.9 million in the second quarter of 2026, 71% of the total and up 52% on the prior quarter, as total revenue rose to $44.8 million from $34.0 million.
- The 20-year Anthropic lease announced in July 2026 covers 401 megawatts of critical IT capacity at the Justified Data Campus in Kentucky and carries projected revenue of roughly $19 billion.
- The company is monetising its Abernathy joint venture interest for approximately $530 million.
Compiled by The InvestorSomething wrong?How this is made
Why it matters
- constraint One tenant sits behind 48% of the contracted book, so the construction calendar at a single Kentucky campus governs the timing of roughly half of TeraWulf's future lease revenue.
- cost 737 contracted megawatts are still to be built, and at the company's own pace of 250 to 500 a year shareholders carry one and a half to three years of capital spending before that rent starts.
- contradiction BofA and Bernstein are constructive on the same contracted book Rothschild Redburn rates Neutral, which puts the disagreement on how much undelivered capacity the share price already holds.
- exposure Non-HPC revenue was flat quarter to quarter at about $13 million. Growth in the reported numbers now depends entirely on delivering data centre capacity on schedule.
Divide the Anthropic contract by its own terms and the price per megawatt falls out: $19bn of projected revenue over 20 years is $950m a year, spread across 401 megawatts of critical IT capacity in Kentucky, or about $2.4m per megawatt annually [4][1]. Cryptobriefing frames the same number as nearly $1bn a year from a single tenant [5]. TeraWulf's HPC line billed $31.9m in the second quarter, an annual rate of $127.6m, which is roughly 13% of what that one lease pays once the megawatts are energised [3][2].
The mix change is sharper than the 71% headline suggests. Work backwards from the 52% sequential increase and first-quarter HPC revenue was about $21.0m, leaving $13.0m of non-HPC revenue in the first quarter against $12.9m in the second [2][3][3]. Total revenue rose $10.8m [6]. All of the increase came from leasing, and the mining and other line was flat.
Rothschild Redburn's caution is about schedule. The note cites construction timelines that can slip and tight labour markets for specialised data centre workers [11], and the gap it is pricing is 737 megawatts: 839 contracted against the 102 operational at Lake Mariner in New York [6][8][5]. At the company's own target of 250 to 500 megawatts of additions a year, that is one and a half to three years of building [7][5]. Cryptobriefing reports that the Anthropic contract buffers demand risk and that supply-side execution is where the thesis gets tested over the next 12 to 24 months [12].
BofA and Bernstein hold more favourable ratings, citing financing progress and the structural pull of hyperscale demand for AI compute [10]. TeraWulf is also monetising its Abernathy joint venture interest for about $530m [9]. The report does not include a share count, so the $15 target cannot be checked against the contracted book from these figures alone.
In my view the shares are priced on energised megawatts, not on the $19bn headline, because rent on a signed 20-year lease is fixed and a late start moves roughly $950m of annual revenue to the right without changing it [4][1]. The counter-case is respectable: if financing is largely done and $530m arrives from Abernathy [9][10], slippage costs interest and holding expense while the tenant stays contracted for two decades [4]. Paul Prager, the chairman and chief executive, and Nazar Khan, the chief technology officer, have run the transition so far [13]. What would prove the cautious read wrong is energised capacity climbing toward that 250 to 500 megawatt annual pace in quarterly disclosure [7]; what would confirm it is Lake Mariner sitting near 102 megawatts while Kentucky dates move [8].
What to watch
- Quarterly disclosure of energised critical IT capacity at Lake Mariner and the Kentucky campus against the 250 to 500 megawatt annual target.
- Completion of the Abernathy joint venture monetisation and where the roughly $530 million is applied.
- Whether Rothschild Redburn, BofA or Bernstein revise ratings as Kentucky construction milestones land.