Product1 distinct publisher3 min readUpdated
The Pike County mega-campus is being financed like utility infrastructure: a supplier-backed lease and power obligation of up to $105bn, with first compute due in 2028.
The Product Desk · Product desk
Compiled by The Product DeskSomething wrong?How this is made
OpenAI, SoftBank's SB Energy and Nvidia have announced a 20-year data center site in Pike County, central Ohio, carrying 8 IT gigawatts of computing capacity drawn from 10 gigawatts of energy [1]. The number that actually explains the project is not the gigawatts: Nvidia has agreed to guarantee up to $105bn in conditional lease and power payment obligations, stepping in as the backstop if OpenAI defaults [2].
That is the mechanism, and it is the product news. Landowners, power developers and lenders signing 20-year paper against this campus are not underwriting OpenAI's future revenue; they are underwriting a guarantee from the chip supplier. In exchange Nvidia takes exclusive rights to supply the chips and a $1.5bn direct equity investment in SB Energy [2], and the site runs exclusively on Nvidia hardware [3].
The unit economics of the backstop are worth holding onto. Spread across 8 IT gigawatts, $105bn is roughly $13bn of guaranteed obligation per IT gigawatt [4]; spread across the 20-year term, roughly $5.3bn a year [5]. Those are ceilings on a conditional exposure, not a bill, but they are the scale at which compute is now being underwritten.
The build is phased. The campus launches with 4.25 gigawatts and an option to expand by 3.75 gigawatts [6], which is how you get to the advertised 8 [7]. OpenAI expects initial computing capacity to come online starting in 2028 as the first phase [8]. On the power side, 10 gigawatts serving 8 IT gigawatts implies 1.25 gigawatts delivered per gigawatt of compute [9], supported by a $4bn-plus local energy infrastructure investment from SoftBank and SB Energy [3]. OpenAI and SB Energy have pledged that local residents will not bear any energy or infrastructure costs [10]. OpenAI puts the labour figures at 35,000 construction jobs and 2,500 permanent positions [11].
Critics immediately called the structure circular, on the grounds that supplier, buyer and investor are propping up each other's balance sheets [12]. Nvidia's Jensen Huang rejected that directly: "Is this circular financing? No", stressing that OpenAI remains directly on the hook for rent payments [13]. His stated rationale is that Nvidia is buying long-lived physical sites it can refill with each chip generation, describing the deal as securing long-lived infrastructure so OpenAI can deploy AI factories that are upgraded repeatedly [14]. Read plainly, the guarantee buys Nvidia a two-decade socket at a site it does not have to re-permit.
Context on siting: the campus sits partly on federal land once used for uranium enrichment [15], part of a broader federal effort to convert Cold War nuclear sites into natural gas-backed AI hubs [16]. In July, NextEra Energy and Brookfield disclosed preliminary plans with the Department of Energy for Kentucky's decommissioned Paducah enrichment complex [17]. For scale, the Ohio site follows last year's $500bn Stargate announcement led by OpenAI, Nvidia, SoftBank and Oracle, which targets 10 gigawatts across multiple sites [18], and exceeds Meta's planned 5-gigawatt Louisiana facility by 3 gigawatts on its own [19], as well as SpaceX's 1-gigawatt Colossus network in Tennessee and Mississippi [20].
Three things to watch. First, how the conditions on the $105bn are drawn, since "conditional" is doing all the work in that sentence [2]. Second, whether buyers negotiating 2028 capacity elsewhere now treat a supplier guarantee as standard terms rather than an Nvidia-specific favour. Third, whether the 3.75-gigawatt option is exercised [6], which is the cleanest signal of whether the first 4.25 gigawatts found paying demand.
Follow any of these and your For You feed starts watching them — no settings page required.
Ranked by verification strength, evidence, and original report placement.
OpenAI, SoftBank's SB Energy and Nvidia announced a 20-year data center site in Pike County, central Ohio, with 8 IT gigawatts of computing capacity powered by 10 gigawatts of energy.
Nvidia agreed to guarantee up to $105 billion in conditional lease and power payment obligations, acting as financial backstop should OpenAI default; in exchange Nvidia gets exclusive rights to supply the chips and a direct $1.5 billion equity investment in SB Energy.
The data center will run exclusively on Nvidia hardware and be supported by a $4 billion-plus local energy infrastructure investment from SoftBank and SB Energy.
The Ohio campus will launch with 4.25 gigawatts of capacity and an option to expand by 3.75 gigawatts.
OpenAI expects the data center's initial computing capacity to come online starting in 2028, the first phase of bringing the mega-campus fully operational.
OpenAI and SB Energy pledged that local residents will not bear any energy or infrastructure costs for the new facility.
Evidence-backed comparisons of source perspectives and observed adoption signals. Read the methodology
Which Builder, Operator, and Investor concerns the observed source mix emphasized—not a truth score.
Evidence, demonstrated adoption, hype gap, incentives, and confidence are assessed independently, each on its own current evidence. How these are measured.
Single outlet, party-supplied figures
Every load-bearing number comes from one trade publication relaying the announcing parties' own statements and press quotes. No contract, filing, regulatory document or independent analyst appears, and two elements are explicitly hedged or unattributed ('reportedly' federal effort; unnamed critics). The only internally checkable material is arithmetic on the parties' own figures.
Announced; nothing in service
There is no deployed capacity, no construction milestone and no operating customer. The earliest compute is expected in 2028, only 4.25 gigawatts is described as launch capacity, and the remaining 3.75 gigawatts is an unexercised option. Adoption evidence is limited to the announcement itself and the disclosed commercial terms.
Headline figures outrun what is committed or verifiable
The advertised 8 gigawatts is the sum of a committed 4.25 GW phase and an unexercised 3.75 GW option, and the $105bn is a conditional ceiling rather than a booked obligation — yet both are presented as headline scale, alongside unverified job targets and a resident-cost pledge with no stated mechanism. Positive but not extreme, because the phasing, the conditionality and the circularity criticism are all disclosed in the same article rather than hidden.
Supplier underwrites its own customer's obligations
The disclosed structure gives every participant a direct interest in the announcement's framing: Nvidia backstops up to $105bn of its largest customer's lease and power obligations while taking exclusive chip-supply rights and equity in the landlord's energy arm; SoftBank/SB Energy get a 20-year anchor tenant; OpenAI gets capacity it does not have to finance on its own balance sheet. The rebuttal to the circularity charge comes from the guarantor's own CEO, and nearly all facts in the cluster originate with these parties.
Terms plausible, verification absent
The capacity, phasing and timeline figures are internally consistent and specific enough to be usable, so the shape of the deal is probably as described. But with one publisher, no primary documents, party-supplied economics, an unnamed critic, a hedged federal-program claim and at least one questionable attribution (Colossus assigned to SpaceX), confidence in the details — especially the guarantee's mechanics — stays below the midpoint.
product
Nvidia's $120bn Ohio backstop puts the chip vendor on the hook for OpenAI's rent4 distinct publishers
invest
Nvidia's newest product is credit: $3bn into SB Energy, $250bn behind OpenAI's rent1 distinct publisher
invest
Nvidia's pre-earnings re-rating is a credit story, not a chip story1 distinct publisher
invest
The 81% Problem: AI's Star CEOs Are Polling Badly With The People They Need To Hire1 distinct publisher
Distinct publishers with included, body-backed reporting in this cluster.
1 article · August 18, 2026