Skip to content

Product1 publisher3 min readPublished

Four-year grid connection waits make the power date the first question in US site selection

JLL says speed to power now drives US site selection, with grid connection waits in major markets topping four years. Parcels on old transmission corridors can now take tenants that identical land next door cannot, AI or otherwise.

The Product Desk · Product desk

Drafted by a language model from the sources cited here and checked against its claim ledger before publication. How we use AISend a correction

Photograph accompanying Four-year grid connection waits make the power date the first question in US site selection
Photo: thenextweb.com

What happened

  • CBRE finds that sites able to deliver power within 18 to 36 months are so sought after that buyers are moving into smaller, less obvious markets.
  • The Texas grid met an all-time record demand of about 91 gigawatts on 22 July 2026, roughly half from natural gas and a third from solar.
  • ERCOT's transmission plan projects a 2030 summer peak above 150 gigawatts, including about 50 gigawatts of large-load growth it does not split by sector.
  • The labels 'powered land' and 'powered site' now appear routinely in listings, while the major research houses publish little defining the category.

Compiled by The Product DeskSomething wrong?How this is made

Why it matters

  • exposure Data center developers bidding for corridor parcels are competing with hydrogen, crypto mining and chemical projects for the same connections, so a forecast built on AI demand alone undercounts the rivals for a site.
  • decision With no standard meaning for 'powered', a buyer has to get a megawatt figure and a delivery date before paying extra for a listing that uses the word.
  • constraint Where existing corridors do not reach, new delivery means regulator-approved transmission costing billions, as the Permian's $7.7bn to $9.1bn import estimate shows, so developers cannot expect the old map to change on a project timeline.

Vicente Garrido, chief financial officer of the Texas power infrastructure developer GoodPeak, described a site that changed category partway through development [11]. "Our Houston campus started with greenfield development for battery storage," he said. "As we worked through the site, we realized it also had access to 138 and 345 kV transmission, a major gas pipeline, and dark fiber. That's when we started looking at the land differently." [12]

GoodPeak found the transmission after it had picked the site. The high-voltage lines and large pipelines that now sort parcels were routed decades ago to serve refineries, towns and industries that have since changed shape [15]. That routing is why two adjacent parcels with the same soil, zoning and highway access can now host different classes of user [16].

Data centers used about 176 terawatt-hours in 2023, or 4.4 percent of US electricity [2]. The Next Web's analysis argues the binding limit is narrower than total supply: how many specific places can receive a great deal of power on a date somebody will lend against [17].

What site buyers actually ask for has four parts. They want a defined quantity of power at one point on the map, by a date, delivered in a way that survives the loss of a piece of equipment [6]. JLL's finding that speed to power is "the primary criteria driving site selection" [3] says the date is now the part that decides. A wait of more than four years is at least 48 months. Against CBRE's 18-to-36-month window, a buyer in a major-market queue is 12 to 30 months short [1].

What teams tell themselves is that this is an AI story. The demand data is broader. In the early-2026 site-selection survey, 82.6 percent rated power at scale very important, the highest intensity score of any infrastructure factor [7]. Those respondents were also planning chemical plants, battery factories and distribution centers [8]. ERCOT's projected 2030 peak sits at least 59 GW above this July's record, about 65 percent higher [2]. Its plan folds data centers in with hydrogen, crypto mining and electrification without splitting them out [9].

Garrido has a test for the "powered land" label. "Powered land should mean more than proximity to infrastructure," he said. "It should mean a site with a credible path to a defined amount of power on a reasonably clear timeline. The more certainty around capacity and timing, the more mature the asset." [13]

The evidence for the land-price half of the argument is thinner. The Next Web says the gap is repricing American land [17], but the article does not include sale prices, premiums, or any lender's view of what delivery date it will finance.

Garrido's two variables make a 2x2 for anyone handed a "powered" listing. One axis asks whether capacity is a defined megawatt figure or a description of nearby lines. The other asks whether delivery lands inside 36 months or out in the four-year queue [1]. Defined capacity inside 36 months is powered land in Garrido's sense [13]. Defined capacity on a queue date is a queue position, and I'd price it as one. A near date without a defined figure has nothing behind it yet. A listing with neither is proximity, the thing Garrido says the label should mean more than [13]. In my view a premium belongs only in the first box, and only after the site passes the fourth test, delivery that survives losing a piece of equipment [6]. The tradeoff is location: CBRE's buyers found that box by moving into smaller, less obvious markets [5].

What to watch

  • Whether JLL, CBRE or another research house publishes a definition of 'powered land' with capacity and timing thresholds.
  • Sale-price data showing a premium for parcels on existing transmission corridors, which would test the claim that land is being repriced.
  • Whether a later ERCOT plan breaks out the 50 GW of large-load growth by sector.
Loading claim ledger
Loading source directory links
Loading share composer
Loading topic controls
Loading related stories