Aligned puts 2GW of data center capacity behind a gas plant in Beaver County
Aligned has started work on a 2GW campus in Shippingport whose electricity is meant to come from a gas plant its landlord has promised. The tenant's first megawatt now depends on that build.
The Product Desk · Product desk

What happened
- Aligned Data Centers has broken ground on Project Phoenix, a 2GW campus of three facilities in the Shippingport Industrial Park in Beaver County, Pennsylvania, about 30 miles northwest of Pittsburgh.
- The park previously held the Bruce Mansfield Power Plant, a 2.49GW coal station run by FirstEnergy and later Energy Harbor that opened in 1976 and shut down in 2019.
- Macquarie Asset Management sold Aligned last year for $40bn to a consortium of the AI Infrastructure Partnership, MGX and BlackRock-owned Global Infrastructure Partners.
Compiled by The Product DeskSomething wrong?How this is made
Why it matters
- constraint The campus load arrives when the gas plant does. Frontier's construction schedule sets when a tenant can energize racks at this site.
- decision Diligence on a site like this turns on who owns the generator, and buyers have to price what happens if the plant is late.
- exposure Uptime at 2GW depends on fuel. Frontier named EQT and National Fuel Gas as serving the plant, which puts gas supply into the tenant's risk register.
- capability With the campus taking roughly 56 percent of the park's stated behind-the-meter capacity, the landlord can sell the same pitch to a second operator on the same land.
The tenant who signs for capacity at Shippingport is underwriting a power project. Aligned said the campus will use its own dedicated on-site power source instead of the local electrical grid [3], and that source is the Shippingport Power Station next door, a former coal plant being redeveloped into a natural gas energy campus [4].
Frontier Group of Companies owns the 660-acre park and bought it from Energy Harbor in 2022 [7]. Last year Frontier said it would develop a 2.7GW gas plant on the site, served by EQT Corporation and National Fuel Gas Company [8].
The stated capacity covers the campus with headroom. A 2.7GW plant against a 2GW campus leaves 0.7GW [2], and Frontier has said the site will be able to offer up to 3.6GW of behind-the-meter capacity [9], so this campus accounts for about 56 percent of that [1]. The planned gas plant is 0.21GW larger than the Bruce Mansfield coal station that ran on the land from 1976 to 2019 [3].
The framing around the groundbreaking is about legacy. "Project Phoenix represents the future of responsible data center development," said Andrew Schaap, CEO of Aligned [11]. Shippingport Mayor John Erickson said "For decades, Shippingport has been defined by powering the country as the birthplace of commercial nuclear energy" [12].
Leaving the grid moves the power dependency. It goes to a landlord and its fuel suppliers. Frontier holds the land and the generation plan [7][8], and in practice the ramp at a campus like this follows the plant's construction schedule. Aligned already runs campuses in Illinois, Texas, Utah, Arizona and Northern Virginia [13], where the power question was settled by someone else.
Whether a behind-the-meter site is safe to lease at this size comes down to which entity owns the generating asset, and what the contract says if first power is late. On the first, the answer here is Frontier. On the second, the announcement says nothing about a tenant for the campus or a date for first power [15].
What to watch
- Whether Frontier's 2.7GW gas plant reaches construction and commercial operation, and on what date.
- Any tenant announcement naming who takes the 2GW, and whether the terms cover late power.
- Whether the remaining behind-the-meter capacity in the 660-acre park is sold to a second operator.