Build1 publisher3 min readPublished
Tower's $4 billion optical-chip build-out in Japan starts inside an already-qualified fab
Tower Semiconductor and Japan will co-invest $4 billion to reach 45,000 300mm-equivalent wafers a month of optical-connectivity capacity by 2029. Until the new fab lands in 2029, growth comes from adding tools to a fab that already ships.
The Engineer · Build desk

What happened
- Tower Semiconductor will put $3 billion and Japan's METI $1 billion into Tower's Japanese fabs, Nikkei reports, for a roughly $4 billion optical-connectivity build-out.
- Tower targets capacity equal to 45,000 300mm wafers a month in Japan by 2029, around 40 times its 2025 level.
- Track One converts the idle 200mm Fab 6 in Arai to 300mm for silicon photonics and optical packaging, and expands output at the 300mm Fab 7 near Uozu.
- Track Two builds a new 300mm fab beside Fab 7 to raise chip output several times over, with a material contribution to results expected in 2029.
Compiled by The EngineerSomething wrong?How this is made
Why it matters
- constraint Through 2028, Tower's supply growth is limited to what added tools at Fab 7 and the converted Fab 6 can deliver, because the new fab only contributes from 2029.
- exposure With more than 80% of contract optical-chip production for servers at one company, a schedule slip at Uozu would reach most contract buyers, Marvell among them.
- cost Tower carries three-quarters of the $4 billion itself, so a late Track One ramp lands mostly on its own balance sheet.
Track One leans on Fab 7 near Uozu [4]. The fab is already fully qualified. It is in mass production of silicon-germanium electronic chips on 65nm-class nodes such as TPS65SG, and of silicon-photonics chips on the 45nm-class TPS45PHD process [5]. Adding equipment there lets Tower raise output as each tool is installed, without waiting for a new fab and its process flows to qualify [6]. Tower has set full production readiness for Track One in the fourth quarter of 2027 [7].
Qualification sets the order of the plan. New capacity goes first onto process flows that already ship, and the building that still has to qualify comes second [6][9]. I think this sequence is right: output grows from the first installed tool, and the schedule risk sits in Track Two [9]. The layout is sensible too. The converted Fab 6 takes on optical-engine assembly, so the end state has two sites making the electronic and photonic chips and one bonding them together [10].
The risk does sit there. Tower's 45,000-wafer target falls in 2029, the same year it expects the new fab beside Fab 7 to start contributing materially [2][9]. The headline figure depends on a fab Tower has yet to construct passing qualification on schedule [9]. Working back from the 40-fold multiple, Tower's Japanese capacity in 2025 was about 1,125 300mm-equivalent wafers a month [1]. Tower plans to hire about 200 people [14].
Tower expects Track One alone to support about $3.6 billion of revenue and $1.2 billion of net profit in FY2028 [8]. The implied net margin is about 33% [2]. That forecast is Tower's claim about its own order book [8]. For it to hold, Track One has to hit its late-2027 readiness date and the added tools have to run full in their first year [7]. METI's $1 billion covers a quarter of the $4 billion total, and Tower funds the rest [3][3].
Nikkei, as reported by Tom's Hardware, says Tower holds more than 80% of contract production of optical communications chips used in servers, with Marvell among its customers [11]. At that share, Tower's capacity schedule is most of the contract market's schedule [11]. Tom's Hardware ties the project's size to fast-growing demand for optical connectivity in AI infrastructure [12]. The report does not include lead times, backlog, or evidence that data-center builds are waiting on optical parts. On this evidence, the dominant contract supplier is committing capital now against demand it expects in 2029 [2][11].
Part of the money is for a market where Tower says it trails [13]. The company concedes that Intel, TSMC and GlobalFoundries are ahead in co-packaged optics, and plans to bring CPO and its precursor technologies to Uozu [13]. It has not disclosed details of that roadmap [13].
What to watch
- Whether Track One reaches full production readiness in the fourth quarter of 2027 as scheduled.
- Construction and qualification milestones for the Track Two fab beside Fab 7 ahead of its expected 2029 contribution.
- Any CPO roadmap Tower publishes for Uozu, given it concedes Intel, TSMC and GlobalFoundries lead.