With a force majeure notice, Oracle hedges against Project Jupiter running late

Oracle shares fell more than 6% on Thursday after it sent a force majeure notice to Blue Owl over Project Jupiter, its New Mexico AI data center. The notice protects Oracle's cash if the site runs late and makes its 2028 date the one lenders and investors now watch.

The Board Room · Leadership desk

Photograph accompanying With a force majeure notice, Oracle hedges against Project Jupiter running late
Photo: forbes.com.au

What happened

  • Sources told Bloomberg that Oracle is not trying to leave as primary tenant but could try to delay payments if the project slips before 2028, though it is unclear whether that would work.
  • Oracle vice president Michael Egbert said the project remains on its planned schedule and that he is confident in moving forward.
  • Blue Owl said it, STACK Infrastructure and Oracle remain fully aligned, and that the notice does not change the project's financial commitments.
  • Project Jupiter is part of the $500 billion Stargate Project that OpenAI, Oracle and SoftBank launched last year.

Compiled by The Board RoomSomething wrong?How this is made

Why it matters

  • exposure If Oracle's deferral argument holds, Blue Owl and whoever finances the developer wait for rent through any delay before 2028, while Oracle's cash stays protected.
  • precedent Oracle calls such notices routine at this scale; if developers accept that, tenants on other large AI sites can be expected to reserve the same delay rights, and leases will be priced with that in mind.
  • decision Companies planning on Jupiter capacity, OpenAI among its intended users, now hold a 2028 date their landlord's tenant has hedged in writing, and have to decide how much schedule slack to carry.

Force majeure is usually invoked when a company faces an earthquake, a storm or another event beyond its control [17]. Oracle has sent one while saying the project is on schedule [5], to keep open an argument that its payments can wait if the building is late [2]. Evercore called the notice "a pretty sensible move" for aligning Oracle's revenue and expenses if the project is delayed, and said it "is not an indication that this project is going away" [9].

RBC Capital Markets analyst Rishi Jaluria made the skeptic's case. The notice "signals the company's own risk assessment on execution has shifted enough to warrant legal cover," he wrote [7]. Oracle's reply came from vice president Michael Egbert. "Force-majeure notices are commonplace in developments of this scale and are often used to preserve contractual rights among project partners. They do not, by themselves, establish a project delay or change delivery expectations," he said [4].

Both statements can be true at once. A tenant can expect to hit its date and still judge that the risk of missing it has grown enough to justify a written claim. Oracle took protection on payments at the cost of a public signal about execution, and its shares were still down 4.4% around midday on Thursday [3].

The board-deck version comes from William Blair: the immediate financial impact should be limited, because Project Jupiter is not expected to contribute revenue in Oracle's current fiscal year [10]. That holds for this year's income statement and leaves out the spending. Oracle reported $28.5 billion of first-quarter capital expenditure, up from $8.5 billion a year earlier, roughly 3.4 times as much [1], and kept its fiscal 2027 capex forecast at $90 billion to $95 billion [11]. That money turns into revenue only when new capacity comes online and converts contract backlog [19]. "Any slippage in the 2028 timeline has direct implications for capacity delivery and revenue recognition given Oracle's supply-constrained posture," Jaluria wrote [8].

This quarter's notice sets up next quarter's financing questions. Oracle secured $18 billion in bank loans for the project, Bloomberg reported last year [12]. Business Insider has reported that some banks and institutional investors grew wary of exposure to Oracle as lenders tried to distribute debt tied to its Stargate data centers [15]. I'd expect those lenders to ask which events Oracle considers beyond its control. The site's known troubles are local. It survived legal challenges that reached New Mexico's Supreme Court [16], and it has drawn protests and lawsuits over its environmental impact and transparency [20]. Recent polling cited by Forbes found a majority of voters from both parties oppose further data center construction [21].

For operators, the record shows a tenant hedging a date. Oracle is reserving the right to pay later if the building is late while staying on as primary tenant [2], at a site meant to host AI infrastructure for companies including Oracle and OpenAI [18]. The reports do not say what event, if any, the notice cites.

What to watch

  • Whether Oracle or Blue Owl discloses which event the notice cites, and whether the developer accepts that payments can be deferred.
  • Oracle's next quarterly update on the 2028 timeline for Project Jupiter and on its $90 billion to $95 billion fiscal 2027 capex forecast.
  • Terms on the next distribution of Stargate-linked debt, given reported lender wariness about Oracle exposure.