Grande Prairie County tightens data centre approvals after residents object to an AI permit

Grande Prairie County now requires commission review of every data centre bid, compliant or not, after residents objected to a five-building AI permit. Developers chasing Alberta's $100 billion target now have to budget for local review time.

The Investor · Invest desk

Photograph accompanying Grande Prairie County tightens data centre approvals after residents object to an AI permit
Photo: yahoo.com

What happened

  • Walton Global, through Stantec Consulting, has asked Edmonton to amend its Energy and Technology Park plan, with public comment open until Oct. 25.
  • Wave Infra has proposed a $300 million, five-megawatt AI research lab and data centre near the Highway 2 corridor between Calgary and Edmonton.
  • Alberta is the destination for 90 percent of Canada's currently planned data centre capacity, according to York University research.

Compiled by The InvestorSomething wrong?How this is made

Why it matters

  • constraint In Grande Prairie County, meeting the bylaw no longer secures a data centre permit, since every application must also clear the planning commission.
  • exposure If Edmonton approves Walton's amendment as filed, 253 hectares would sit outside the park's eco-industrial principles, so the environmental terms become what residents contest.
  • precedent Grande Prairie changed its process over a single permit that met the rules, and with Edmonton and Red Deer County in similar discussions, Alberta site selection now has to account for municipal review time.

On paper the approval near Sexsmith was routine. The County's land-use requirements have included data centres for years [4], and the applicant was not disclosed [3]. Five buildings of 80 by 180 feet come to 72,000 square feet of footprint [1], plus 15 make-up air generators [3]. "The permit was approved in accordance with the existing land-use bylaw, adopted in 2003," the County said in a statement. "While the requirements of the bylaw process were met, we recognize that this application has prompted important discussions about transparency, public input and how projects of this type are considered under the current process." [5]

The fix lands on the next applicant. The County said modern data centres may fit the letter of its bylaw but not its spirit, given their scale, and future applications now go to the municipal planning commission whether or not they meet bylaw standards [6]. A compliant site in the County now also needs the commission's sign-off [6].

Walton Global's Edmonton filing is the better puzzle. The Calgary land company plans a hyperscale-ready campus at the Edmonton Energy and Technology Park [7]. The City has said AI data centres count as heavy industrial use and would be permitted within the existing petrochemical area, even though nobody contemplated them when the plan was written in 2010 [10]. So a data centre can already go on petrochemical land. Stantec Consulting filed the amendment for Walton [8], and it asks for three changes: data centres and their power generation written into the medium industrial category, 253 hectares moved from petrochemical to medium industrial, and the eco-industrial principles limited to petrochemical land [9]. Taken together, those 253 hectares would leave the principles behind when they change category [2].

The principles exist to mitigate the industrial area's environmental impact [9]. The park was envisioned as a "world-class eco-industrial park that combines economic opportunity, ecological integrity, and efficient use of land and resources" [14]. In my view, what Walton gets out of the application is relief from those conditions, and the comment window that closes Oct. 25 [8] is where residents can contest that. The other reading is that Walton wants certainty. Plan text that names data centres and power generation outright means a hyperscale campus does not depend on the City's interpretation of heavy industrial use. The filing fits both readings.

Wave Infra's proposal near Highway 2 is $300 million for five megawatts [11], or $60 million a megawatt [3]. The project includes an AI research lab [11], so the figure does not tell an investor what Alberta data centre capacity costs to build.

There are three ways this can go. Municipalities may add review steps and still approve most projects, so developers pay in time. They may attach conditions, as Edmonton could by keeping eco-industrial principles on Walton's 253 hectares. Or a commission may refuse a project that met its zoning. I'd expect one of the first two. Alberta has 22 data centres operating and dozens more proposed [2], and it draws 90 percent of Canada's planned capacity under rules that favour development, according to York University research [12]. Edmonton and Red Deer County are having similar discussions [13], so I'd expect more review steps even without refusals. The view is wrong the first time a planning body turns down a data centre that met its bylaw. From then on, a developer could not count on compliance to win approval.

What to watch

  • Edmonton's decision after the Oct. 25 comment deadline on whether eco-industrial principles still apply to Walton's 253 hectares.
  • Whether Red Deer County adds a commission review step for compliant data centre applications like Grande Prairie's.
  • Whether Walton names a tenant or power source for its hyperscale-ready campus once the plan text allows associated power generation.