Four Texas data center filings schedule $1.2bn of construction into 2029
Digital Realty, CoreSite, DataBank and Colovore have filed construction calendars with Texas licensing regulators for new buildings around Dallas and Austin. The earliest of the four is due to finish in December 2028.
The Product Desk · Product desk

What happened
- Digital Realty, Colovore, Hut 8, CoreSite and DataBank have all filed to build data centers in Texas, three of them around Dallas, one outside Austin in Hutto and one in Corpus Christi.
- Digital Realty is putting $300 million into DFW45, a 672,000 sq ft building at 1602 Ferris Road on its Digital Garland campus in Dallas County.
- CoreSite, owned by American Tower, is entering Texas with DA1, a $200 million, 230,000 sq ft two-story building in the Irving area of Dallas County.
- DataBank has filed for DFW15, a $425 million, 443,680 sq ft two-story building on Batchler Road in Red Oak, Ellis County.
- Colovore's $280 million project in Hutto is a single-story 192,695 sq ft facility on what is currently greenfield land in Williamson County.
Compiled by The Product DeskSomething wrong?How this is made
Why it matters
- constraint A Dallas or Austin deployment with a 2027 deadline has to be served out of buildings already standing, because the earliest of these four cannot hand over space until the end of 2028.
- cost Whoever leases the high-density hall carries the cost of the density, since it is about 1.9 times more expensive per megawatt to build than the conventional suite.
- decision Colovore's rack spec sets a hardware floor for its Austin tenants: bring gear that can draw 600kW in a rack, or lease a cheaper building elsewhere.
- precedent A Texas campus announced in 2026 is better modelled as 2029 capacity, going by how long these operators took to get from public reveal to groundbreaking.
The engineer costing out AI capacity around Dallas for 2027 wants two numbers from any project: megawatts and a completion date. The filings, reported by DataCenterDynamics, give the dates in four cases out of five [1]. Digital Realty's DFW45 in Garland runs June 2026 to January 2029, 31 months and the longest window filed [3][10]. At the other end, CoreSite needs 20 months for DA1 in Irving, April 2027 to December 2028 [4][10]. Colovore has December 2026 to December 2028 in Hutto [7]. DataBank's DFW15 in Red Oak finishes last, in August 2029, from a February 2027 start [5].
Only two of the filings put dollars and megawatts in the same document. Digital Realty's $300 million buys 80MW, or $3.75 million per MW [2][3][2]. Colovore's $280 million buys 40MW, or $7 million per MW [7][8][3]. Per square foot that is $446 against $1,453 [4]. Both companies size their capacity in 8MW blocks, ten suites at Garland and five halls in Hutto [3][8]. The four projects together come to $1.205 billion and 1,538,375 sq ft [1][9]. The report does not include megawatt figures for DA1 or DFW15 [4][5].
What Colovore is selling in Hutto is density. Its website says the 40MW AUS01 will be able to offer more than 600kW per rack across five 8MW data halls [8]. The company launched in 2013 with liquid-cooled racks capable of up to 35kW, so the Austin target is roughly 17 times its own starting point [9][6]. A tenant that cannot draw 600kW in a rack pays $1,453 a square foot for room it will not fill [4].
The filings are not new projects. Digital Realty announced a Garland campus on W Campbell Road in 2017 and an expansion in 2018, and it already runs more than a dozen data centers in the Dallas-Fort Worth area [12][13]. DataBank announced its Red Oak campus in September 2024, and DFW15 breaks ground about 29 months after that [6][7]. Colovore's Hutto plan surfaced in late 2024, when it filed Project Raptor with the Hutto city council, and construction starts two years later [10][8]. CoreSite's Irving site came up in planning commission meetings in February, where the eventual plan was described as three two-story buildings across some 37 acres [11].
So the sorting question on a campus announcement is whether a licensing filing exists yet, and whether that filing pairs a dollar figure with a megawatt figure. Among these five operators, four clear the first and two clear the second [11]. DataBank's first Red Oak phase, four buildings on Batchler Road, is already under construction [6].
What to watch
- Hut 8's Corpus Christi project, once cost and megawatt figures for the filing are published.
- Whether CoreSite files for the second and third buildings on the Irving site, which planning commission discussions put at three across some 37 acres.
- Colovore's listed Dallas projects, the 44.8MW DFW01 in Mesquite and the 32MW DFW02 in Fort Worth, reaching a filing with construction dates.