Amazon's 20-year contract pays for a 190 MW nuclear uprate at Calvert Cliffs due in 2030-32
Amazon's 20-year, 690 MW power deal with Constellation backs more than $3 billion of work at Calvert Cliffs, including a 190 MW uprate due in 2030-32. Only that 190 MW is new output, and it still has to clear NRC reviews that have not been scheduled.
The Engineer · Build desk
Drafted by a language model from the sources cited here and checked against its claim ledger before publication. How we use AISend a correction

What happened
- Constellation has not said what equipment it will change, who will build it, or how the $3 billion divides among the uprate, modernization and longer operation.
- The uprate plan predates Amazon: a February 2025 package of about $100 million covered pumps, motors, valves, control-rod systems and a 13-kV transformer.
- Constellation says Amazon's long-term commitment is what now makes the uprate possible.
- The NRC met privately with Constellation on Oct. 1 about upcoming license amendment requests for both units and did not say whether they cover the uprate.
- Unit 1 is licensed through July 31, 2034 and Unit 2 through Aug. 13, 2036, and Constellation wants another two decades of operation.
Compiled by The EngineerSomething wrong?How this is made
Why it matters
- constraint Neither Amazon nor Constellation can attach a regulatory date to the 2030-32 target until the NRC accepts an application and sets a review schedule.
- exposure Amazon carries renewal risk. The later years of its 20-year term depend on two reactors getting license renewals the NRC has not yet granted.
- capability By Constellation's account, a single long-term buyer is enough to move an uprate at an operating reactor from planned to funded.
The 690 MW in the contract includes the uprate [2]. Take out the 190 MW and about 500 MW is output the plant already produces [2]. That is roughly 28% of its 1.79 GW [3]. The uprate adds about 10.6% to current capacity [1]. Constellation's preliminary analysis in February 2025 put the possible gain at roughly 10%, so the figure has held [8].
That February 2025 announcement came five to seven years before the 2030-32 window for first new power [5]. Constellation is also spending $68 million on 24 electrical breakers to upgrade the plant substation [9]. In November 2025 it sized the uprate and said "new equipment and technology" would be required [10]. Its public description of the work Amazon is funding stops at "state-of-the-art improvements" across the plant [6].
The regulator has no schedule yet. Scott Burnell, a senior public affairs officer at the NRC, told ENR that plant owners file uprate and license-renewal requests publicly. He said the commission can provide a review schedule only after it finds an application acceptable [13]. The agency also held an earlier closed session with Constellation, on Feb. 25, about potential power-uprate requests at plants it did not identify [14].
The license dates are the constraint that is easy to miss. The same contract pays for the extra megawatts and for the license years they need. If the uprate arrives at the end of its window, Unit 1 has about two years of operation left under its current license [4]. A 20-year contract signed this decade outlasts both units' current licenses [6]. ENR reports that the deal gives Constellation the revenue certainty to seek another two decades of operation [4]. The more than $3 billion is split across the uprate, plant modernization and work supporting longer operation [6].
Calvert Cliffs has done this twice before. In 1977 it became the first US plant approved for a power uprate: a 5.5% stretch uprate of 140 MWt on each of its two Combustion Engineering pressurized-water reactors [15]. In 2009 the NRC approved a 1.4% measurement-uncertainty-recapture uprate of 37 MWt per unit [16]. Those figures are thermal megawatts. The 190 MW is quoted as an increase in output [1], so the earlier percentages and the new 10.6% are measured on different bases.
ENR's report covers one plant and does not address regional supply or demand. It cannot support a general claim that power will be scarce. For this contract, I'd plan on 2032, the late end of Constellation's window. I'd also treat the 190 MW as conditional on an uprate review and a license renewal that have yet to happen [3][13][5].
What to watch
- Constellation publicly filing the uprate license amendment requests for Units 1 and 2. Only then can the NRC accept them and set a review schedule.
- A license renewal application for Calvert Cliffs ahead of Unit 1's July 31, 2034 expiry.
- Constellation naming its contractors and saying how the $3 billion splits among the uprate, modernization and life extension.