Nabiax commits €800m to Alcalá megawatts that arrive in phases through 2029
The cornerstone at Alcalá de Henares starts a build that adds up to 100MW of IT capacity in stages through 2029. Nabiax runs about 33MW in Spain today, so most of the 135MW it will hold there is still a construction schedule.