Published Build3 min read
Half of planned data centers will miss 2028, and the bottleneck is permits, not chips
Goldman Sachs expects only about half of planned US data-center capacity to arrive on schedule by 2028, down from a historical 72%. Only 802 of 3,969 announced sites are actually being built.
Written for builders.See today for builders

What happened
- Goldman Sachs estimates that historically about 72% of planned data-center capacity was brought into operation on schedule.
- Goldman Sachs estimates that by 2028 only about half of new AI compute capacity may come online on schedule.
- The expected on-time delivery rate falls by about 22 percentage points, from 72% historically to about 50% by 2028.
- Stanford University's AI Index Report counted 5,427 data centers operating in the United States at the end of last year.
- AI companies announced construction of a further 3,969 data centers in the United States.
Compiled by The EngineerSomething wrong?How this is made
Why it matters
Goldman Sachs expects only about half of new US AI compute capacity to be running on schedule by 2028, against a historical rate of roughly 72% of planned data-center capacity delivered on time, according to CNN's account of the bank's work [1][2]. That is a 22 point drop in delivery reliability [3], and it means any compute roadmap anchored to announced megawatts is overstated by construction, not by chip supply.
The pipeline arithmetic is worse than the schedule slippage implies. Stanford's AI Index Report counted 5,427 data centers operating in the United States at the end of last year, while AI companies announced 3,969 more, of which only 802 are actually under construction [4][5][6]. That is about 20% of the announced set in the ground [7], with the announcements alone representing a 73% addition to the existing stock [8]. Goldman's explanation is mundane: developers file in several jurisdictions at once and later pick the site with the best terms [9]. The same project can appear in multiple local pipelines and never net out of the headline total.
JPMorgan puts this year's AI infrastructure investment at $750 billion, but about 60% of the capacity meant to be live by the end of 2027 has not entered construction, and a further 7% of projects already started are behind schedule [10][11][12]. A typical build runs 18 to 24 months [13], so the un-started portion of that 2027 cohort is already out of calendar.
Chips have not stopped mattering: TSMC makes essentially all leading AI processors, including Nvidia Blackwell and AMD MI300X [14]. But the queue has moved. Goldman argues the main obstacle is permitting duration rather than outright bans, even though roughly ten states have weighed moratoriums and New York and Texas have imposed temporary restrictions [15][16]. Data centers consume about 8% of US electricity, which the American Edge Project projects rising to 12% by 2028, a 50% increase in share [17][18][19]. JPMorgan records a tripling of wait times for step-up transformers [20]; GE Vernova says generator orders have doubled in five years to $200 billion [21]; inflation in transformers and power regulators has been the second fastest of 47 categories tracked by the Bureau of Labor Statistics since 2020 [22]. The American Edge Project estimates the announced plans need an additional 500,000 electricians, 300,000 welders and 550,000 plumbers [23]. Gallup found 71% of Americans do not support these facilities being built [24].
Columbia Business School real estate professor Stijn Van Nieuwerburgh puts it in portfolio terms: of the 565 gigawatts AI companies currently plan, perhaps 180 gigawatts get built over the next decade [25], about 32% [26], with two thirds of the portfolio "implausible" in his words [27]. Even that reduced case implies roughly $10 trillion of investment, 50% more than the 19th century railroad buildout, the largest previous US investment boom [28][29]. Spread over ten years that is about $1 trillion a year, above the current $750 billion run rate [30]. The modest scenario is still an acceleration.
Watch the conversion rate, not the announcements: the 802 figure is the only number in this set that reflects committed capital and a poured foundation. Watch transformer and generator lead times, which set the physical floor on delivery dates regardless of financing. Watch component pricing bleed into consumer goods, where Reuters reports memory demand from AI data centers pushed Apple to raise prices on some MacBooks and iPads in July, with personal computers and peripherals up 3.5% in a month [31][32][33]. And note the Federal Reserve's position, per Reuters, that the direct effect of AI on US inflation and employment remains limited and contradictory [34], which is a reminder that the constraint story and the macro story are still running on different clocks.
Claim ledger
Ranked by verification strength, evidence, and original report placement.
- [1]
Goldman Sachs estimates that historically about 72% of planned data-center capacity was brought into operation on schedule.
- [2]
Goldman Sachs estimates that by 2028 only about half of new AI compute capacity may come online on schedule.
- [4]
Stanford University's AI Index Report counted 5,427 data centers operating in the United States at the end of last year.
- [5]
AI companies announced construction of a further 3,969 data centers in the United States.
- [6]
Only 802 of the announced data centers are actually under construction.
- [9]
Goldman Sachs says developers often file applications in several regions in parallel and later choose the single site with the best conditions.
Sources & coverage · 1 publisher
The reporting this story was synthesized from, earliest first. Every link goes to the original.
- mezha.netyaroslavAug 12У США гальмує бум ШІ: більшість запланованих дата-центрів можуть не збудувати
Cited in this coverage: Goldman Sachs, reported by CNN via mezha.net
Cited in this coverage: Stanford AI Index Report, via mezha.net/CNN
Cited in this coverage: Goldman Sachs, via mezha.net/CNN
Cited in this coverage: JPMorgan, via mezha.net/CNN
Cited in this coverage: mezha.net summarising CNN
Cited in this coverage: American Edge Project, via mezha.net/CNN
Cited in this coverage: GE Vernova, via mezha.net/CNN
Cited in this coverage: Bureau of Labor Statistics data, via mezha.net/CNN
Cited in this coverage: Gallup, via mezha.net/CNN
Cited in this coverage: Stijn Van Nieuwerburgh, Columbia Business School, via mezha.net/CNN
Cited in this coverage: Stijn Van Nieuwerburgh, quoted via mezha.net/CNN
Cited in this coverage: Reuters, via mezha.net
Cited in this coverage: Morgan Stanley, via Reuters and mezha.net

